Meter data for Import Projects differ from other NYGATS projects. To report Meter data for Non-Import Projects in the NYGATS, please visit the User Training Guide for Qualified Independent Party (QIP) Specific Instructions - How to Report Meter Data (Link Here)
Reporting Hourly Data for Import Projects
QIPs reporting Hourly generation data for Import Projects, must use the following CSV File format to report hourly meter readings:
- NYGATS ID:
- The NYGATS ID Number is assigned to the project by NYGATS after the project registration is submitted by the Account Holder.
- Do not include the Project Type Prefix that precedes the ID (i.e.GEN, AGG, IMP)
-
- QIP ID:
- QIP assigned ID. Must be unique for each Import Project
-
- Date:
- Date of Generation (MM/DD/YYYY)
-
- Hour:
- Hour of the day Generation occurred. Formatted as numeric figures (1-24)
The DST Long Day should include an extra hour listed as 2*
- Hour of the day Generation occurred. Formatted as numeric figures (1-24)
- Total MWh -
- Total hourly Generation (MWh) for the hour and day.
Additional and Related Resources
Qualified Independent Party Guidelines - NYSERDA QIP Requirments containing detailed guidelines
Qualified Independent Party (QIP) Guidelines and Information - User Training and background for QIPs